اختبار ذاتي: دورة ادارة مشاريع PMP (نقابة المهندسين ) 150سؤال تحاكي الامتحان الدولي

السؤال 1 من 149

الزمن المتبقي: 180 دقيقة

An organization need to implement a new regulation inquired by government with specific date when this regulation will be enforced; However, the government has only provided high-level information on the regulation’s requirements. Therefore, changes in definitions are to be expected due to uncertainty. Which life cycle should the project manager use for this project?