السؤال 1 من 149

الزمن المتبقي: 180 دقيقة

A project lead is working on an agile project to build the team’s vision, including the decision-making process. It was decided that the team will vote on items, and if 80% of the team agrees on a decision, then it will be carried forward. At the first technical design meeting, all team members agree on a decision that project lead strongly disagrees with. How should the project lead proceed?